Laundry room plumbing
It's amazing what pretty weather will bring.... inside work! Today the plumber came and installed most of the drain lines for all of the sinks, washing machine, toilets etc. Nice to see this major project under way. In addition the heating and air guys came and marked off where the vents will go in each of the rooms as well as the air return vents.the master bath sink drains and vent
The framing crew was also busy putting nailers up for drywall and finished sheeting the gable ends. They are also preparing to tie all of the trusses together with long runs of 2 X 4s that will run the length of the house in the attic. I believe the plans call for 6 individual runs from one end of the house to the other. The house is so much cooler now and with the titanium sheeting on the roof, it will stay dry until the shingles go on in another couple of weeks. Tomorrow we go shopping for interior doors, a fireplace and logs, and some furniture after an early morning on the lake. Sounds good to me.